Safety Case
Type of Documents | Duration | Reference [1] | |
---|---|---|---|
Safety Case | Fixed Facility | 6 months | 13.(1)(b) |
Mobile Facility | 3 months | 14.(1)(b) | |
Combined Operation | 21 days | 15.(1) | |
Decommissioning and Restoration | n/a | 16.(1)(b) | |
Notification | Design Notification | 6 months | 11.(1) |
Well operation | 21 days | 12.(1) | |
Insertion of hollow pipe in the well | 10 days | 12.(2) | |
Altering of the construction of the well | 10 days | 12.(2) | |
Decommissioning and Restoration | n/a | 11A.(1) |
The duty holder shall review submit a summary of review within 5 years of date of issue or last review 18.(2). If there is a Material Change DH need to submit SC to competent authority and notify the authority as soon as practicable
- [1] Workplace Safety and Health (Facilities) (Control of Major Accident Hazards) Regulations, 2013 Workplace Safety and Health Order, 2009
Reference: Schedule 8, Workplace Safety and Health Order (Facilities) (Control of major Accident Hazards Regulations (COMAH), 2013
Type of Documents | Fees | |
---|---|---|
Notifications | Design Notification for Fixed Facility | BND 50,000 per notification |
Material Change to Design Notification for Fixed Facility | BND 10,000 per notification | |
Decommissioning and Restoration for Fixed Facility | BND 20,000 per notification | |
Material Change to Decommissioning and Restoration for Fixed Facility | BND 10,000 per notification | |
Notifications of Well Operation | BND 10,000 per notification | |
Safety Case | Onshore Fixed Facilites | BND 100,000 annually |
Offshore Fixed Facilities - One or two premises | BND 100,000 annually | |
Offshore Fixed Facilities - more than two premises | BND 200,000 annually | |
Material Change to Fixed Facility Safety Case | BND 20,000 per submission | |
Mobile Facility | BND 100,000 annually | |
Material Change to Mobile Facility | BND 10,000 per submission | |
Decommissioning and Restoration Safety Case | BND 50,000 per submission | |
Material Change to Decommissioning and Restoration Safety Case | BND 10,000 per submission | |
Combined Operations Safety Case | BND 25,000 per submission | |
Material Change to Combined Operations Safety Case | BND 10,000 per submission |
Process to apply FRN
